We would like the following job done. Hi What price approx should i be paying for this job to be done External rendering of walls that have been previously rendered and painted. – please see pictures at www.ourhandyman.co.uk/render Render to be smooth render finish. Materials and labour to be included in price. Work to start around 10th – 17th August 2009
I have just tried these pics and i can open them. Are u getting the links to the pics. http://www.ourhandyman.co.uk/render/
I have just made a slide show for anyone else having problems viewing thanks http://ourhandyman.co.uk/slideshow/
Number of things: 1. the in-situ render is run down too low bridging any DPC. 2. the third elevation of the extn. is not shown. 3. there is a lot of pipework/penetrations and clutter on the facework. this means extra work. 4. is there access for debris and materials? 5. render is always a 2-man job - therefore, 6 man days plus materials for price.