Had to change my 1st floor after BCO passed.

Discussion in 'Builders' Talk' started by Crazyhorse, Jul 23, 2020.

  1. Crazyhorse

    Crazyhorse Member

    Ok, so my first floor in my extension went in and was passed by BCO during Covid lockdown via Photos in email. A new inspector came out and noticed the bricky has broken the external leaf corble finish to attach the joist runner flush.

    Now the new BCO wants the runner attached to the internal leaf with Chemical anchors and the joists bricked in and supported by the external leaf. This now means I also have to re hang my joist hangers on the opposite end in my thermalite blocks as well. Should these be cut in and fixed with chemical resin aswell?

    Thoughts please!!
     
  2. stevie22

    stevie22 Screwfix Select

    Picture?
     
  3. Crazyhorse

    Crazyhorse Member

    nothing to picture it’s all down now.. start again...
     
  4. Crazyhorse

    Crazyhorse Member

    Hope this helps.

    both pics upside down?
     

    Attached Files:

    Last edited: Jul 24, 2020

Share This Page

  1. This site uses cookies to help personalise content, tailor your experience and to keep you logged in if you register.
    By continuing to use this site, you are consenting to our use of cookies.
    Dismiss Notice