EXTRA DEEP FOUNDATIONS

Discussion in 'Builders' Talk' started by SandyM737, Dec 27, 2016.

  1. SandyM737

    SandyM737 New Member

    Hi all.

    Planning a small rear extension. Our post code is RH12 5XQ.

    Building Control have told me due to the proximity of a neighbours mature oak I will need more than the standard foundations (i.e. option B below)

    I need a ball park as to how much this is likely to cost, if it's as bad I think it will kill the budget and we won't be able to afford any of it and I won't bother getting the drawings done.

    Tried a few local builders with this question but they didn't even bother to reply.

    A) Standard 10 meters of trench 1m deep + 13m2 of concrete floor.
    B) Standard 10 meters of trench 2m deep + compressible material + 13m2 suspended concrete floor.

    What would be most helpful to us is, if someone could say something like;

    for just the foundations and assuming there are no snags, then for each you're looking at around
    A) ? thousand
    B) ? thousand

    I know there are a ton of things that will affect the cost of any job. I just need some helpful person to take a stab at it. Any ideas on this will be so helpful, thanks.
     
  2. CGN

    CGN Screwfix Select

    The problem is, that you won't really get anyone to quote because you haven't got any drawings. A lot of time and effort goes into doing a proper quote from a reputable builder. At this stage, you're sat on the fence a bit (through no fault of your own) and as there is plenty of work about, you may struggle to get the info you need.

    What is the access like? Can you get a machine in to dig out?
     
    Joe95 and KIAB like this.
  3. sospan

    sospan Screwfix Select

    Is 10m the perimeter or 10m in length of one side ?

    It may sound strange but it is harder to dig a deep hole that is short in length than a loner one.

    Since building control has specified a beam and block type floor you could consider piling our screw in foundations that will eliminate the need for conventional digging.
     
  4. Phil the Paver

    Phil the Paver Screwfix Select

    Surprised B.C. didn't mention a raft.
     
  5. SandyM737

    SandyM737 New Member

    Trench lengths are 3, 3 and 4m.

    Isn't suspended the same as raft?
     
  6. KIAB

    KIAB Super Member

    Supended floor could be concrete beams laid out & infilled with concrete blocks (block & beam), whereas as raft concrete floor is reinforced with steel mesh.
    And with raft foundation, the two most frequently used is the flat raft and the wide toe raft.
     
    Last edited: Dec 28, 2016
  7. SandyM737

    SandyM737 New Member

    As I said in my original.
    Suspended, with concrete beams not timber.
     
  8. SandyM737

    SandyM737 New Member

    There is access for a mini digger.
     
  9. sospan

    sospan Screwfix Select

    The lengths are part of your problem. Digging 2m is at or near the maxim of most mini diggers around 1.5t. The problem is squaring off the bottom of the trench where it meets the house - due to the depth and angle of the bucket. Normally you would finish this by hand but at that depth (requires shoring) and at a 600mm width it going to be difficult. So either side of your footing trench you may have to get the machine to batter back the footing to get access and then shutter back up to the correct height.

    It does seem accademic to put the foundations this deep on three sides without putting them against the house as well. Since the house is unlikely to have foundations this deep and the roots will work their way in through the open side of the extension.

    The other thing to take into account is that you are going to need around 3 skips to take away all the waste material

    Rather than try general builders, I would contact some groundwork specialists and then once the foundations are in place a lot of general builders will be more amenable to give quotes
     
    Joe95 and KIAB like this.
  10. KIAB

    KIAB Super Member

    The JCB 8014 CTS mini digger has a digging depth of 2.648m, which is the best in it's weight class of 1634kg(1.5 ton).:eek:

    I agree with Sos, very,very few general builders would want to tackle this job.
     
    Last edited: Dec 28, 2016
    Joe95 likes this.
  11. SandyM737

    SandyM737 New Member

    Hi Guys. Thanks ever so much for your posts.

    Even though you give no estimates is all valuable feedback.

    Lots to think about. Never thought of trying a 'groundwork' company, though they were only for commercial. Will try that next.

    This is a standard semi D, my big worry is that at the point where the new trenches meets the house at the rear corner of my property and close to the boundary of my neighbours at 2m deep isn't there a serious risk of movement of the existing foundations and therefore major structural problems?
     
  12. KIAB

    KIAB Super Member

    Last edited: Dec 28, 2016
  13. sospan

    sospan Screwfix Select

    Some rough costs off the top of my head digging the foundations is probably going to be :

    2 days hire of digger and driver £500
    2 days hire of skip loader £120
    3 skips £450
    3 shuttering ply and misc timber £100
    manual labour 2 people for 2 days £600

    So probably set your expectations around £2,000 as we don't know soil conditions, access, local costs etc.

    Foundations

    2 full loads £1400
    if it can go from the mixer straight into the footings 1 days labour £150

    So again £2,000

    Obviously very rough costs
     
  14. KIAB

    KIAB Super Member

    [​IMG]

    We have a few of these around here, they have a reach of around 13 metre with the 360 degree rotatheam conveyor. .
     
    Joe95 likes this.
  15. sospan

    sospan Screwfix Select

    Yep, one of the worst jobs is when the shutes don't reach and you have to put it on the deck because the mixer won't wait to put in barrows. Then the race to level it before it goes off - and of course it is never the right weather either too hot or rainy
     
  16. Joe95

    Joe95 Screwfix Select

    That is a very well designed conveyor, it solves a lot of the issues with unstable ground too. Must cost a fair few quid:eek:
    Rotatheam build some very good conveyors, there is one truck round here with the sprider, seen it in action a few times:cool:. Good way to loose the barrows.
     
  17. sospan

    sospan Screwfix Select

    When the were repair the gas mains down here they crew had a truck with a giant vacuum on an arm, as the digger worked the arm sucked up the spoil and dumped it in the back of the truck !
     
    Joe95 likes this.
  18. stevie22

    stevie22 Screwfix Select

    As said above many, many variables. I would guess you will add around £3k with the extra depth (there will be extra dig with the suspended floor as you generally need 225 clear gap under and some authorities want 300).

    You say it's an oak that's causing the problem: how far away is it and how high is it now. Also what type of oak is it? NHBC list English, Red, Holm & Turkey in their tables and the max height varies between 16 & 24m: this makes a huge difference. If the tree is not full height then you should be able to argue that if the current height/distance/type indicates a depth <1500mm then the ground under the new floor will be isolated from the tree and the heave precautions are not required and a ground baring slab will suffice.

    The founds will still need to go to a depth dictated by the max height of the tree but this doesn't need to be constant: it is entirely reasonable to step the founds as the distance to the tree increases.
     
    Joe95 and KIAB like this.
  19. sospan

    sospan Screwfix Select

    I would never argue with a Building inspector over the potential for root damage. The tree will no doubt have a preservation order, If he decides to get awkward he can just say that the roots are with the RPA (root preservation area) and then you have to go and do battle on a whole new front and engage with arbologist and costs will spiral as you argue compliance and non compliance

    Sometimes best to agree
     
  20. stevie22

    stevie22 Screwfix Select

    There's a world of difference between arguing with BCO: which as said you'll generally lose and clarifying things to use the design codes properly.

    I generally assume an oak to be english at 20m max but if your BCO is very cautious then he might say red at 24m max.

    As an example take an oak at 12m in high PI soil NHBC chart 1:
    If Red D/H = 12/24 = 0.5 so 2.5 depth
    but if Holm D/H = 12/16 = 0.75 so 2 deep

    Going further if the oak is off to one side then the distance to the far foundation is going to be 16m so for the Holm D/H is now 1.0 so 1.5 deep.

    Get someone to do you a design PROPERLY looking at the foundation depth: a few minutes of calculating beats the bejazus out of digging oversize holes and filling them with concrete.
     
    KIAB likes this.

Share This Page

  1. This site uses cookies to help personalise content, tailor your experience and to keep you logged in if you register.
    By continuing to use this site, you are consenting to our use of cookies.
    Dismiss Notice